Below is the most recent update from Delta Group regarding Demolition works at 12 Riverside quay.
Further updates will be added as we get them.
Internal Strip Out has commenced.
Perimeter Scaffold Erection – 8/04/24
Alimak Installation – 15/04/24
Tower Crane Installation – 29/04/24
Demolition (Starting at the Plantroom) – 6/05/24